Day 1

The preparation team arrive at the same time as the plant for that day. They will remove your existing driveway and then dig out the sub base down to as far as is necessary all muck is then taken away by grab lorry. The area is now ready to take the new sub base which again will be delivered right on time, in the form of 40mm to dust grade 1 M.O.T. Stone.

The next job is to set the shuttering which will form the edge of the driveway.

The hardcore is then distributed around the site and once in position will be compacted with a Whacker plate. This will provide a solid surface which will be ready to take the formulation. You can walk or drive on the driveway at this stage and the site will be left clean and tidy at the end of day one.

 

Day 2

The formulation arrives and that is also inspected to make sure it is the correct consistency and has got the required ingredients. It is then carefully distributed around the site. We use a tool called a roller bug which is 2 rollers made of steel mesh.  This is used to level the formulation and also pushes down any aggregate below the surface. We don’t tamp it down as this would destroy the air entrainment.

Next we use a magnesium bull float which will level the surface and also bring moisture to the surface. The reason for a magnesium float is that it keeps the surface of the formulation ‘open’ , a steel float for example would close it which would be detrimental to the next stage, where we apply the colour. The colour is a permanent U.V. stable quartz colour hardener, which means that it will not fade, and also it hardens the surface of the driveway. The colour penetrates down into the open formulation. It is then floated again using a steel float which closes the surface.

The next stage for us is to apply a colour release agent to the surface. The pattern is embossed into the driveway using a series of 12-15 flexible mats. Each mat is placed on the surface and weight is applied to create a pattern. The release agent allows the mat to be lifted once the pattern has been embossed.

There are several reasons why we use 12 – 15 mats, firstly it enables us to emboss a large area quickly so as to maintain the quality embossing, and not have pattern imperfections. The second reason is that each mat is slightly different so if you can get a random or natural looking effect, rather than a constantly repeating pattern like you would get if you only had 2 mats.

 

Day 3

We cut the expansion joint and then power wash off about 80% of the release agent. The remainder will provide an authentic look to the driveway.

 

Day 4

We come back and seal the driveway using the unique formulation Xyleene based acrylic sealer which gives a permanent seal to the driveway so that you won’t have any stains or maintenance.